Projects
"Jump on Board!" - Victoria Marine Rescue Society's fundraising Campaign
The VMRS has launched a comprehensive and well focused fundraising campaign. Our intent is to raise the organization's visibility in the community and increase public and corporate awareness of the important service we provide. We are confident that a public and corporate sector that is much more aware of the community need that we meet, will be forthcoming with increased donations and/or sponsorships to help us meet our funding target.
Vessel Now Under Construction! (Sep 4/07)

(Nov 11/07)

New Rescue Vessel Project
In response to the critical need to expand Victoria's marine search and rescue capability, the
Victoria Marine Rescue Society with the support of the Canadian Coast Guard and Canadian Coast
Guard Auxiliary - Pacific has launched a campaign to raise $645,000 for the purchase and operation
of a new fast response vessel to serve the Victoria, Esquimalt, and West Shore waterfronts and the
surrounding waters of Juan de Fuca Strait. In an environment of greatly increased commercial and
recreational activity on the water, VMRS recognizes a pressing need to replace it's eight meter
rigid hull inflatable with a new all weather vessel. This will increase our capacity to respond
to medical evacuations, missing person searches, boating emergencies, and large scale disasters.
|
Some highlights of this vessel will be:
- Four person crew
- Ability to respond over a larger area
- Enclosed cabin to protect our crews against elements
- Capacity for 50 passengers
- Stable first aid platform
- Fire-fighting & self-righting capabilities
- Maneuverable
- Fast response (30+ knots)
|
|
Timeline
| Project Tasks |
Target Completion |
| Fundraising |
Sep 2007 |
| Crew Training |
Oct 2007 |
| Vessel Construction |
Dec 2007 |
| Sea Trials |
Jan 2008 |
| Transport Canada Inspection and Certification |
Feb 2008 |
| Official Launch and Dedication |
Feb 2008 |
Budget
| Budget Item |
$ Amount |
| Operational Training |
$10,000 |
| Business Plan |
$1,300 |
| Administration costs |
$500 |
| Vessel Drawings |
$24,900 |
| Safety and Construction Changes |
$65,300 |
| Capital Costs (Boat and Equipment) |
$543,000 |
| Total Project Costs |
$645,000 |
|